Costs for Alternative Scenarios
| Scenario 1 Renal Dosing Database Exists | Scenario 2 CDSS Product Exists | Scenario 3 CPOE System Does Not Require Special Programmer | ||||
| Activity | Hours | Cost ($) | Hours | Cost ($) | Hours | Cost ($) |
| Project management | 53.5 | 1,480 | 53.5 | 1,480 | 80.25 | 2,220 |
| Preparing contents of the CDSS | 241.2 | 13,728 | 241.2 | 13,728 | 482.25 | 27,456 |
| Informatics project management | 121.7 | 4,987 | 60.9 | 2,494 | 121.7 | 4,987 |
| Preparing blueprints and instructions for progammer | 50.8 | 1,870 | 12.7 | 467 | 50.8 | 1,870 |
| Programming | 110.5 | 8,813 | 27.63 | 2,203 | 110.5 | 3,413 |
| Testing and implementing | 79.0 | 3,322 | 79.0 | 3,322 | 79.0 | 3,322 |
| Total | 656.7 | 34,201 | 474.93 | 23,695 | 924.5 | 43,268 |